 Performance Measures Legend

 

Complete

Complete

Going Well

On Target

Concern

Concern

Some Concern

Serious Issue

Construction

Design/Construction

Complete

Complete

Design

Design

 

 

Helix High School

Executive Director:           Dr. Douglas Smith

7323 University Ave
La Mesa, CA 91941
Ph: 619.644.1940
FAX: 619.462.9257

 Prop H Performance Measures

Project NamePhase StatusBudgetSchedulePhase TypePercent Complete
Underground InfrastructureComplete1/2A Infrastructure 100%
Building 10Complete2B Modernization 100%
Building 100Complete2B Modernization 100%
Building 200Complete2B Modernization 100%
Building 300 - LibraryComplete2B Modernization 100%
Electrical/Low Voltage HousingComplete2B Modernization 100%
ADA Upgrades/Student Parking LotComplete2B Modernization 100%
Science BuildingConstruction3A New Building 70%

 Prop U Performance Measures

Project NamePhase StatusBudgetSchedulePhase TypePercent Complete
New Project2009 25%