Project Name

Science Building  

Phase Type

3A New Building 

Campus

06 - Granite Hills 

Phase Status

Construction 

Percent Complete

65% 

Scope of Project

The scope of the New Science Building Project (3A) encompasses designing a one-story (14,033 GSF) science classroom building.  The program consists of ten (8) classrooms (2 Chemistry; 4 Biology; 2 Physics) and New Restrooms.  The building will be designed to the current District Standards as to performance capabilities, and per Education Code and building codes (ADA compliance, Fire Life Safety, Structural).  Site Preparation work consists of the relocation of one classroom; add 3 relocatable classrooms; demolition of 2 buildings, slabs & foundations.  The underground utility infrastructure (wet & dry) utilities will removed, rerouted, installed (as required or requested) consistent with the underground utilities infrastructure plan

Budget

Going Well 

Schedule

Going Well 

Architect

HMC 

Construction Manager

 

Project Manager

Dena Johnson

Multi-Prime Contractors

Jaynes 

Project Image

 

Design Report

Schematic Design 

Project Schedule

Summary Project Schedule 

Construction Report

Weekly Construction Progress Report 