Project Name
Building 10
Phase Type
2B Modernization
Campus
02 - Helix Charter
Phase Status
Complete
Percent Complete
100%
Scope of Project
Modernization of 10 standard classrooms & restroom facilities, consistent with the District Standards and performance capablities within each classroom (New roof systems, HVAC, data power & power) and perform all required underground infrastructure (electrical, gas, water, sanitary sewer, drainage, communications, fire alarm and data) work. Abate all hazardous materials within the classroom buildings; address the removal of barriers consistent with the ADA transition plan.
Schedule has been impacted due to extensive termite damage, and the find of live termites within the building.
Budget
Project Complete
Schedule
Project Complete
Architect
HMC
Construction Manager
Turner Construction
Project Manager
Debbie Murray
Multi-Prime Contractors
Able Heating & Air Conditioning; Baddi Enterprises, Inc.; Commercial & Industrial Roofing; EC Constructors, Inc; ProSpectra Flooring; Ranbar Plumbing; Sadler Electric, Inc.; Soltek Pacific; Straight Line General Contracting
Project Image
Design Report
Project Schedule
Summary Project Schedule
Construction Report
Weekly Construction Progress Report