Project Name

Gymnasium Restroom ADA Remodel 

Phase Type

2B Modernization 

Campus

05 - El Capitan 

Phase Status

Complete 

Percent Complete

100% 

Scope of Project

Perform all required underground infrastructure (electrical, gas, water, sanitary sewer, drainage, communications, fire alarm and data) work. Abate all hazardous materials within the restroom facility; address the removal of barriers consistent with the ADA transition plan.

Budget

Project Complete 

Schedule

Project Complete 

Architect

Harley Ellis Devereaux 

Construction Manager

Erickson Hall 

Project Manager

Dena Johnson

Multi-Prime Contractors

Davis Mechanical; EC Constructors; Lemon Grove Sheet Metal; Precision Electric; Prospectra Flooring; Protech Roofing; Soltek Pacific 

Project Image

 

Design Report

 

Project Schedule

Summary Project Schedule 

Construction Report

Summary Weekly Construction Report 

Prop

Prop H 
Attachments
Created at 3/15/2008 9:59 AM  by Debbie Murray 
Last modified at 6/5/2009 9:39 AM  by System Account