Project Name

Boys and Girls Locker Facility  

Phase Type

3A New Building 

Campus

01 - Grossmont 

Phase Status

Complete 

Percent Complete

100% 

Scope of Project

Construct a new 9,250 GSF Boys & Girls Locker, Showers, Team Room, to replace the existing Carl Perkins Building being demolished to make way for the new science building

Budget

Project Complete 

Schedule

Project Complete 

Architect

Harley Ellis Devereaux 

Construction Manager

Turner 

Project Manager

Debbie Murray

Multi-Prime Contractors

Jaynes 

Project Image

 

Design Report

Schematic Design 

Project Schedule

Summary Project Schedule 

Construction Report

 

Prop

Prop H 
Attachments
Created at 3/7/2008 12:42 PM  by Debbie Murray 