Project Name
Science Building
Phase Type
3A New Building
Campus
02 - Helix Charter
Phase Status
Construction
Percent Complete
99%
Scope of Project
The scope of the New Science Building Project (3A) encompasses designing a two-story (17,033 GSF) science classroom building. The program consists of ten (10) classrooms (4 Chemistry; 4 Biology; 2 Physics) and New Restrooms. The building will be designed to the current District Standards as to performance capabilities, and per Education Code and building codes (ADA compliance, Fire Life Safety, Structural). Site Preparation includes the demolition and removal of four (4) relocatable classroom buildings. The underground utility infrastructure (wet & dry) utilities will removed, rerouted, installed (as required or requested) consistent with the underground utilities infrastructure plan
Budget
Going Well
Schedule
Concern
Architect
Harley Ellis Devereaux
Construction Manager
Turner
Project Manager
Debbie Murray
Multi-Prime Contractors
Project Image
Design Report
Project Schedule
Summary Project Schedule
Construction Report
Prop
Prop H
Attachments
Created at 3/6/2008 4:51 PM by System Account
Last modified at 6/3/2010 10:06 AM by Debbie Murray
Use this page to add attachments to an item.
Name